Critical Path Analysis Practice

Practise CPA by filling in the EST and LFT directly on the network diagram. Change the level below before starting a new question.

Easy The durations are already shown on the paths. Students work out the EST, LFT and critical path.
Hard The durations are hidden. Students must use the task table and type the duration values onto the paths before working out EST, LFT and the critical path.
Mode: Easy

Project

Fill in the diagram directly.
Project duration: ?
Hint: Start at node 1 with 0 and work forwards first.

Task Table

All scenarios are linked to business projects. In Hard mode, use this table to work out the durations and type them onto the paths.

Critical Path

Enter like A-B-D-F
Score
Project duration
?

Total Float

Float = LFT of end node − EST of start node − Duration. Enter 0 for critical activities.