Critical Path Analysis Practice

Practise CPA by filling in the EST and LFT directly on the network diagram. Change the level below before starting a new question.

Easy The durations are already shown on the paths. Students work out the EST, LFT and critical path.
Hard The durations are hidden. Students must use the task table and type the duration values onto the paths before working out EST, LFT and the critical path.
Mode: Easy

Project

Fill in the diagram directly.
Project duration: ?
Hint: Start at node 1 with 0 and work forwards first.

Task Table

All scenarios are linked to business projects. In Hard mode, use this table to work out the durations and type them onto the paths.

Critical Path

Enter like A-B-D-F
Score
–
Project duration
?

Total Float

Float = LFT of end node − EST of start node − Duration. Enter 0 for critical activities.
Want precise targets on your exam answers?

Get clear, actionable feedback and next steps — linked directly to what you wrote.

How to work out the critical path: a worked example

Critical path analysis (CPA) shows the shortest time a project can take and which activities cannot be delayed without delaying the whole project. Here's a small example you can follow before trying the practice tool above.

ActivityDuration (days)Depends on
A3—
B2—
C4A
D3B
E2C and D
  1. Forward pass (earliest start time, EST): A and B start at 0. C can start at day 3 and D at day 2. E has to wait for both, so its EST is the later of 3 + 4 = 7 and 2 + 3 = 5, which is 7. The project takes 7 + 2 = 9 days.
  2. Backward pass (latest finish time, LFT): start with 9 at the end node. E must start by day 7, so C and D must finish by 7. A must then finish by 7 − 4 = 3, and B by 7 − 3 = 4.
  3. Critical path: A–C–E (3 + 4 + 2 = 9 days). Every activity on it has zero float.
  4. Total float for D: LFT of its end node (7) − EST of its start node (2) − duration (3) = 2 days. B also has 2 days of float.

In the exam: the calculation is only part of the marks. A Level questions often ask you to evaluate CPA, so be ready to explain its limits: durations are estimates, the network can become complex, and it doesn't show the cost or quality of each activity.